Work continues on the Fall Hill Avenue overpass, and that means overnight travel delays on I-95.
According to the Virginia Department of Transportation (VDOT), crews will be cleaning and staining the new bridge at mile marker 131 in Fredericksburg, which is a part of the Fall Hill Avenue widening project.
More on the lane closures and delays, from VDOT:
Lanes on I-95 will be closed on the following schedule, weather permitting.
Sunday, Feb. 19 and Monday, Feb. 20
I-95 Northbound at mile marker 131 (Fall Hill Avenue)
- Double lane closure 9 p.m. ˗˗ 1 a.m.
I-95 Southbound at mile marker 131 (Fall Hill Avenue)
- Double lane closure 1 a.m. ˗˗ 5 a.m.
- All lanes reopen to traffic by 5 a.m.
Tuesday, Feb. 21 and Wednesday, Feb. 22
I˗95 Southbound at mile marker 131 (Fall Hill Avenue)
- Single lane closure at 9:30 p.m.
- Double lane closure at 10 p.m.
- All lanes re-open to traffic by 5 a.m.
Message boards will warn travelers to stay alert for work zones ahead and possible delays.
Motorists may consider using Route 1 as an alternate route.